Energy Projects Near You

Walpole Sub Station, Walpole Bank (100 MW battery storage, REPD 12683)

Walpole Sub Station, Walpole Bank is a 100 MW battery storage project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 July 2023, not yet built; the record was last updated on 24 February 2026. REPD also records that the planning permission expired on 4 July 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtmay be out of datestatus in REPD
24 February 2026record last updated
King's Lynn and West Norfolkcouncil area

REPD also records that the planning permission expired on 4 July 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
8 November 2022Application submitted
4 July 2023Planning permission granted
4 July 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
24 February 2026
Operator or applicant
Henry Energy Limited
Planning authority
King's Lynn and West Norfolk
Planning application reference
22/02021/F
Address (REPD)
Opposite Walpole Sub Station Walpole Bank Walpole St Andrew
Council area (by location)
King's Lynn and West Norfolk
Time to decision
34 weeks
Name in REPD
Walpole Sub Station, Walpole Bank - Battery Storage
REPD reference
12683

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Walpole Sub Station, Walpole Bankbattery storage100approved, not built0.2
Walpole Bankbattery storage100application submitted0.3
Walpole St Andrewbattery storage100approved, not built0.3
Walpole Banksolar farm40under construction0.7
Model Farmbattery storage49.9approved, not built1.0
North Walpole, St Peterbattery storage100approved, not built1.0
Rose And Crown Farmsolar farm30operational1.7
Gunthorpe Road, Marsh Solar Farmsolar farm49.9approved, not built2.4
Lapwing Fen 2 Battery Storage Plantbattery storage250under construction2.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7252, 0.2091).