Energy Projects Near You

Lapwing Fen 2 Battery Storage Plant (250 MW)

Lapwing Fen 2 Battery Storage Plant is a 250 MW battery storage project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2022; the record was last updated on 8 June 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

250 MWbattery storage
under constructionstatus in REPD
8 June 2022record last updated
Fenlandcouncil area

Planning timeline

DateStage
25 November 2019Application submitted
27 April 2020Planning permission granted
1 June 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
250 MW
Status (REPD)
under construction
Record last updated
8 June 2022
Operator or applicant
Tribus Clean Energy
Planning authority
King's Lynn and West Norfolk
Planning application reference
19/02004/FM
Address (REPD)
Flower Farm, The Marsh, Walpole St. Andrew, Wisbech,
Council area (by location)
Fenland
Time to decision
22 weeks
Name in REPD
Lapwing Fen 2 - Battery Storage Plant
REPD reference
7614

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lapwing Fen II, Crown Farmbattery storage49.9approved, not built0.6
Gunthorpe Road, Marsh Solar Farmsolar farm49.9approved, not built1.4
Model Farmbattery storage49.9approved, not built1.6
Walpole Banksolar farm40under construction1.9
Walpole St Andrewbattery storage100approved, not built2.2
Walpole Sub Station, Walpole Bankbattery storage100approved, not built2.3
Rose And Crown Farmsolar farm30operational2.5
The Grange Wind Farmwind farm14operational2.5
Walpole Sub Station, Walpole Bankbattery storage100approved, not built2.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7286, 0.1722).