The Grange Wind Farm (14 MW)
The Grange Wind Farm is a 14 MW wind farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2013; the record was last updated on 19 April 2013.
14 MWwind farm
operationalstatus in REPD
19 April 2013record last updated
South Hollandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 June 2009 | Application submitted |
| 16 April 2010 | Refused by the planning authority |
| 15 October 2010 | Planning permission granted |
| 15 October 2010 | Appeal allowed |
| 1 September 2012 | Construction started |
| 1 March 2013 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 14 MW
- Status (REPD)
- operational
- Record last updated
- 19 April 2013
- Operator or applicant
- Renewable Energy Systems (RES)
- Planning authority
- South Holland
- Planning application reference
- H21-0439-09
- Turbines
- 7
- Address (REPD)
- Middle Road, Tydd St. Mary, Wisbech, Cambridge
- Council area (by location)
- South Holland
- Time to decision
- 69 weeks
- REPD reference
- 3671
Who decides
| Applications | South Holland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 44 | 10,236 |
| Refused | 11 (25%) | 19% |
| Solar refused | 7 of 26 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 2 of 15 | 16% |
| Median time from submission to decision | 13.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 6 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: Lincolnshire, South Holland.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Gunthorpe Road, Marsh Solar Farm | solar farm | 49.9 | approved, not built | 1.7 |
| Sutton Bridge Solar Farm | solar farm | 49.9 | operational | 2.0 |
| Lapwing Fen 2 Battery Storage Plant | battery storage | 250 | under construction | 2.5 |
| Lapwing Fen II, Crown Farm | battery storage | 49.9 | approved, not built | 3.1 |
| Model Farm | battery storage | 49.9 | approved, not built | 3.2 |
| Walpole Bank | solar farm | 40 | under construction | 3.8 |
| Walpole St Andrew | battery storage | 100 | approved, not built | 3.8 |
| Walpole Sub Station, Walpole Bank | battery storage | 100 | approved, not built | 3.9 |
| Walpole Sub Station, Walpole Bank | battery storage | 100 | approved, not built | 4.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7506, 0.1662).