Energy Projects Near You

The Grange Wind Farm (14 MW)

The Grange Wind Farm is a 14 MW wind farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2013; the record was last updated on 19 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWwind farm
operationalstatus in REPD
19 April 2013record last updated
South Hollandcouncil area

Planning timeline

DateStage
17 June 2009Application submitted
16 April 2010Refused by the planning authority
15 October 2010Planning permission granted
15 October 2010Appeal allowed
1 September 2012Construction started
1 March 2013Operational

Project details

Technology
wind farm
Capacity
14 MW
Status (REPD)
operational
Record last updated
19 April 2013
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
South Holland
Planning application reference
H21-0439-09
Turbines
7
Address (REPD)
Middle Road, Tydd St. Mary, Wisbech, Cambridge
Council area (by location)
South Holland
Time to decision
69 weeks
REPD reference
3671

Who decides

ApplicationsSouth HollandUK
Decided applications (solar, wind, battery)4410,236
Refused11 (25%)19%
Solar refused7 of 2612%
Onshore wind refused2 of 345%
Battery storage refused2 of 1516%
Median time from submission to decision13.8 weeks17.0 weeks
Appeals lodged / allowed5 / 6—

UK: all UK planning authorities. Counted under these REPD planning authority names: Lincolnshire, South Holland.

Other large projects within 10 km

ProjectTypeMWStatuskm
Gunthorpe Road, Marsh Solar Farmsolar farm49.9approved, not built1.7
Sutton Bridge Solar Farmsolar farm49.9operational2.0
Lapwing Fen 2 Battery Storage Plantbattery storage250under construction2.5
Lapwing Fen II, Crown Farmbattery storage49.9approved, not built3.1
Model Farmbattery storage49.9approved, not built3.2
Walpole Banksolar farm40under construction3.8
Walpole St Andrewbattery storage100approved, not built3.8
Walpole Sub Station, Walpole Bankbattery storage100approved, not built3.9
Walpole Sub Station, Walpole Bankbattery storage100approved, not built4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7506, 0.1662).