Energy Projects Near You

Solar, wind and battery projects near Wisbech (PE14)

30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE14 (King's Lynn and West Norfolk): 1 is waiting for a planning decision, 17 approved but not yet running, 9 operational. The largest live scheme is Walsoken, Burrettgate Road (200 MW battery storage, approved on 25 July 2025, not yet built), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30projects within 10 km
1awaiting a decision
17approved, not running
9operational

Projects within 10 km of PE14

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wisbech Solar Farmsolar farmsolar farm3.5operationalupdated Mar 2016Oct 2014granted Jan 2015Mar 2016Fenland3.1
Walsoken, Burrettgate Roadbattery storagebattery storage200approved, not builtupdated Aug 2025Dec 2023granted Jul 2025Aug 2025King's Lynn and West Norfolk3.2
Meerdyke Solar Panels & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Mar 2024Nov 2022granted Mar 2024Mar 2024King's Lynn and West Norfolk3.9
Marshlands Farmwind farmwind farm57application withdrawnupdated Jul 2009Oct 2008—Jul 2009King's Lynn and West Norfolk4.6
Whitemill Wind Farmwind farmwind farm14operationalupdated Aug 2012Nov 2007granted Nov 2008Aug 2012Fenland7.0
Coldham Estate Solar Farmsolar farmsolar farm10permission expiredupdated Oct 2020Sep 2019granted Dec 2019Oct 2020Fenland7.1
Coldham Estate Solar Farmbattery storagebattery storage6permission expiredupdated Dec 2019Sep 2019granted Dec 2021Dec 2019Fenland7.1
Coldham Hallwind farmwind farm14operationalupdated May 2009Jan 2002granted Oct 2002May 2009Fenland7.5
Rose And Crown Farmsolar farmsolar farm30operationalupdated Jun 2016Feb 2014granted Sep 2015Jun 2016King's Lynn and West Norfolk8.0
North Walpole, St Peterbattery storagebattery storage100approved, not built may be out of dateupdated Oct 2021Sep 2021granted Jun 2022Oct 2021King's Lynn and West Norfolk8.9
Coldhamwind farmwind farm16operationalupdated Apr 2011Aug 1999granted Oct 2004Apr 2011Fenland9.0
Walpole Banksolar farmsolar farm40under constructionupdated Nov 2024Sep 2020granted Jan 2021Nov 2024King's Lynn and West Norfolk9.2
Walpole Bankbattery storagebattery storage100application submitted may be out of dateupdated Apr 2023Nov 2022—Apr 2023King's Lynn and West Norfolk9.2
Walpole Sub Station, Walpole Bankbattery storagebattery storage100approved, not built may be out of dateupdated Jun 2026Dec 2022granted Jul 2023Jun 2026King's Lynn and West Norfolk9.4
Walpole Sub Station, Walpole Bankbattery storagebattery storage100approved, not built may be out of dateupdated Feb 2026Nov 2022granted Jul 2023Feb 2026King's Lynn and West Norfolk9.5
Walpole St Andrewbattery storagebattery storage100approved, not built may be out of dateupdated Jul 2024Feb 2022granted Sep 2022Jul 2024King's Lynn and West Norfolk9.5
Lapwing Fen II, Crown Farmbattery storagebattery storage49.9approved, not built may be out of dateupdated Nov 2022Nov 2019granted Mar 2020Nov 2022Fenland9.6
March Sewage Treatment Workswind turbinewind turbine2operationalupdated Apr 2013Jul 2007granted Feb 2009Apr 2013Fenland9.6
Stags Holtwind farmwind farm18operationalupdated May 2009Dec 2001granted May 2002May 2009Fenland9.7
Stags Holt Extensionwind turbinewind turbine2operationalupdated Jul 2013Jun 2007granted Oct 2008Jul 2013Fenland9.7
Model Farmbattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2022Aug 2021granted Jan 2022Feb 2022King's Lynn and West Norfolk9.8
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fenmarc Produce, Gosmoor Lane Solar Farm & Battery Storagesolar farmsolar farm1approved, not builtupdated Oct 2023Apr 2023granted Oct 2023Oct 2023Fenland1.7
Fenmarc Produce, Gosmoor Lane Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Oct 2023Apr 2023granted Oct 2023Oct 2023Fenland1.7
Boleness Roadrooftop solarrooftop solar0.4approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Fenland3.7
Meerdyke Solar Panels & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2024Nov 2022granted Mar 2024Mar 2024King's Lynn and West Norfolk3.9
Cromwell Road Tescorooftop solarrooftop solar0.8approved, not builtupdated Sep 2023Jan 2020granted Mar 2020Sep 2023Fenland4.6
Princes Truna Limited, Walsokenrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024King's Lynn and West Norfolk4.9
Askew And Barrett Pulses, Smeeth Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023King's Lynn and West Norfolk5.6
Wisbech St Mary Sports & Community Centre Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Fenland7.5
Volmary Sitesolar farmsolar farm0.2operationalupdated Jul 2019Jan 2019granted Mar 2019Jul 2019Fenland7.8

Distance from the average position of the PE14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7033090.9
Rooftop solar404002
Wind farm500400
Wind turbine200200
Battery storage1211000800

MW in pipeline: pending, approved and under-construction capacity.

How King's Lynn and West Norfolk decides solar, wind and battery applications

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in King's Lynn and West Norfolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE14, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.