Energy Projects Near You

Coldham Hall (14 MW wind farm)

Coldham Hall is a 14 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2005; the record was last updated on 6 May 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
Fenlandcouncil area

Planning timeline

DateStage
25 January 2002Application submitted
26 October 2002Planning permission granted
1 August 2005Operational

Project details

Technology
wind farm
Capacity
14 MW
Status (REPD)
operational
Record last updated
6 May 2009
Operator or applicant
Co-op
Planning authority
Fenland
Planning application reference
F/YR02/0143/F
Turbines
8
Address (REPD)
Coldham Hall Nr the Coldham Estate Cambridgeshire
Council area (by location)
Fenland
Time to decision
39 weeks
REPD reference
3479

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coldham Estate Solar Farmsolar farm10permission expired1.3
Coldhamwind farm16operational1.5
Whitemill Wind Farmwind farm14operational2.1
Stags Holtwind farm18operational3.7
West Fen Farm, Whitemoor Roadbattery storage30application submitted6.4
West Fen Farm, Whitemoor Road Solar Farmsolar farm49.8application submitted6.4
Boardinghouse Wind Farmwind farm10.3operational8.4
Walsoken, Burrettgate Roadbattery storage200approved, not built8.6
Tydd Solar Farmbattery storage15refused9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.603, 0.1149).