Stags Holt (18 MW wind farm)

Stags Holt is an 18 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2007; the record was last updated on 6 May 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
Fenlandcouncil area

Planning timeline

DateStage
21 December 2001Application submitted
23 May 2002Planning permission granted
1 April 2007Construction started
1 October 2007Operational

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
6 May 2009
Operator or applicant
Powergen / Wind Prospects
Planning authority
Fenland
Planning application reference
F/YR01/1269/F
Turbines
9
Address (REPD)
March Cambridgeshire
Council area (by location)
Fenland
Time to decision
22 weeks
REPD reference
3129

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitemill Wind Farmwind farm14operational2.8
Coldham Estate Solar Farmsolar farm10permission expired3.0
Coldhamwind farm16operational3.6
Coldham Hallwind farm14operational3.7
West Fen Farm, Whitemoor Road Solar Farmsolar farm49.8application submitted5.3
West Fen Farm, Whitemoor Roadbattery storage30application submitted5.3
Boardinghouse Wind Farmwind farm10.3operational5.7
Knights End Road Solar Farmsolar farm5permission expired8.1
Ranson Moor (phase 1)wind farm6operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5698, 0.1233).