Coldham Estate Solar Farm (10 MW)

Coldham Estate Solar Farm is a 10 MW solar farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 17 December 2022; the record was last updated on 7 October 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
permission expiredstatus in REPD
7 October 2020record last updated
Fenlandcouncil area

Planning timeline

DateStage
17 September 2019Application submitted
17 December 2019Planning permission granted
17 December 2022Permission expired

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
permission expired
Record last updated
7 October 2020
Operator or applicant
ScottishPower Renewables
Planning authority
Fenland
Planning application reference
F/YR19/0810/F
Site area
29.3 ha
Address (REPD)
Solar Farm, March Road, Coldham, Wisbech, Cambridgeshire
Council area (by location)
Fenland
Time to decision
13 weeks
REPD reference
7676

The scheme also includes 6 MW of battery storage, recorded separately in REPD (permission expired).

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitemill Wind Farmwind farm14operational0.8
Coldham Hallwind farm14operational1.3
Coldhamwind farm16operational2.4
Stags Holtwind farm18operational3.0
West Fen Farm, Whitemoor Road Solar Farmsolar farm49.8application submitted6.8
West Fen Farm, Whitemoor Roadbattery storage30application submitted6.8
Boardinghouse Wind Farmwind farm10.3operational8.3
Walsoken, Burrettgate Roadbattery storage200approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5963, 0.1313).