Whitemill Wind Farm (14 MW)

Whitemill Wind Farm is a 14 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 May 2012; the record was last updated on 24 August 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWwind farm
operationalstatus in REPD
24 August 2012record last updated
Fenlandcouncil area

Planning timeline

DateStage
2 November 2007Application submitted
25 November 2008Planning permission granted
2 May 2012Operational

Project details

Technology
wind farm
Capacity
14 MW
Status (REPD)
operational
Record last updated
24 August 2012
Operator or applicant
Co-operative Energy
Planning authority
Fenland
Planning application reference
F/YR07/1184/F
Turbines
7
Address (REPD)
Coldham Estate, Coldham, Wisbech
Council area (by location)
Fenland
Time to decision
56 weeks
REPD reference
3480

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coldham Estate Solar Farmsolar farm10permission expired0.8
Coldham Hallwind farm14operational2.1
Stags Holtwind farm18operational2.8
Coldhamwind farm16operational3.1
West Fen Farm, Whitemoor Road Solar Farmsolar farm49.8application submitted7.2
West Fen Farm, Whitemoor Roadbattery storage30application submitted7.2
Boardinghouse Wind Farmwind farm10.3operational8.4
Walsoken, Burrettgate Roadbattery storage200approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5926, 0.1406).