Energy Projects Near You

Meerdyke Solar Panels & Battery Storage (49.9 MW)

Meerdyke Solar Panels & Battery Storage is a 49.9 MW solar farm project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 March 2024, not yet built; the record was last updated on 14 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
14 March 2024record last updated
King's Lynn and West Norfolkcouncil area

Planning timeline

DateStage
17 November 2022Application submitted
26 May 2023Appeal lodged
6 March 2024Refused by the planning authority
6 March 2024Planning permission granted
6 March 2024Appeal allowed
6 March 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
14 March 2024
Operator or applicant
Downing Renewable Developments Llp
Planning authority
King's Lynn and West Norfolk
Planning application reference
22/01987/FM
Appeal reference
23/00023/REF
Site area
87.0 ha
Address (REPD)
SE of Poplar Farm Harps Hall Road Walton Highway
Council area (by location)
King's Lynn and West Norfolk
Time to decision
68 weeks
Contracts for Difference
AR6
REPD reference
12717

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Walsoken, Burrettgate Roadbattery storage200approved, not built2.6
Marshlands Farmwind farm57application withdrawn4.7
Rose And Crown Farmsolar farm30operational4.7
North Walpole, St Peterbattery storage100approved, not built5.2
Walpole Bankbattery storage100application submitted5.6
Walpole Banksolar farm40under construction5.8
Walpole Sub Station, Walpole Bankbattery storage100approved, not built5.9
Walpole Sub Station, Walpole Bankbattery storage100approved, not built5.9
Walpole St Andrewbattery storage100approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6732, 0.2257).