Ongar Hill Wind Farm (22 MW)
Ongar Hill Wind Farm is a 22 MW wind farm project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 14 June 2016; the record was last updated on 1 September 2016.
22 MWwind farm
refused on appealstatus in REPD
1 September 2016record last updated
King's Lynn and West Norfolkcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 7 March 2012 | Application submitted |
| 3 February 2015 | Refused by the planning authority |
| 6 October 2015 | Appeal lodged |
| 14 June 2016 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 22 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 1 September 2016
- Operator or applicant
- Coriolis Energy and Falck Renewables
- Planning authority
- King's Lynn and West Norfolk
- Planning application reference
- 12/00321/FM
- Appeal reference
- APP/V2635/W/15/3132154
- Turbines
- 9
- Council area (by location)
- King's Lynn and West Norfolk
- Time to decision
- 152 weeks
- REPD reference
- 4554
Who decides
| Applications | King's Lynn and West Norfolk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 60 | 10,236 |
| Refused | 11 (18%) | 19% |
| Solar refused | 5 of 38 | 12% |
| Onshore wind refused | 3 of 6 | 45% |
| Battery storage refused | 3 of 16 | 16% |
| Median time from submission to decision | 14.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Estuary Farm, Edward Benefer Way Solar Farm & Battery Storage | solar farm | 49.9 | approved, not built | 4.7 |
| High Road, Saddlebow | battery storage | 50 | approved, not built | 7.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7865, 0.3424).