Treading Wind Farm - South Holland (5 MW)

Treading Wind Farm - South Holland is a 5 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 September 2012; the record was last updated on 8 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
refusedstatus in REPD
8 October 2013record last updated
Fenlandcouncil area

Planning timeline

DateStage
8 February 2011Application submitted
19 September 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
8 October 2013
Operator or applicant
Wind Ventures
Planning authority
Fenland
Planning application reference
H19-0081-11
Turbines
2
Address (REPD)
Sutton St Edmund, Spalding, Lincs
Council area (by location)
Fenland
Time to decision
84 weeks
REPD reference
3796

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Treading Wind Farm - Fenlandwind farm15refused on appeal0.6
Delph Wind Farmwind farm27application withdrawn0.8
Tydd Solar Farmbattery storage15refused1.5
Tydd Solar Farmsolar farm24.9refused1.5
Tydd Solar Farmsolar farm24.9refused1.6
Tydd Solar Farmbattery storage15refused1.6
Fendyke Solar Farm - Extensionsolar farm5refused on appeal3.7
Fendyke Solar Farmsolar farm17.6abandoned4.9
Fendyke Farm Solar Farmsolar farm20refused5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6925, 0.0566).