Energy Projects Near You

Tydd Solar Farm (15 MW, REPD 16512)

Tydd Solar Farm is a 15 MW battery storage project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 3 June 2025; the record was last updated on 1 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWbattery storage
refusedstatus in REPD
1 July 2025record last updated
Fenlandcouncil area

Planning timeline

DateStage
30 May 2024Application submitted
3 June 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
15 MW
Status (REPD)
refused
Record last updated
1 July 2025
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Fenland
Planning application reference
F/YR24/0457/F
Address (REPD)
E/O Guanockgate Road, Sutton St Edmund, Spalding, Wisbech
Council area (by location)
Fenland
Time to decision
53 weeks
REPD reference
16512

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tydd Solar Farmsolar farm24.9refused<0.1
Tydd Solar Farmbattery storage15refused0.1
Tydd Solar Farmsolar farm24.9refused0.1
Delph Wind Farmwind farm27application withdrawn1.1
Treading Wind Farm - South Hollandwind farm5refused1.5
Treading Wind Farm - Fenlandwind farm15refused on appeal2.2
Fendyke Solar Farm - Extensionsolar farm5refused on appeal4.9
Treading Bank Solar Farmsolar farm49.9refused5.0
Fendyke Solar Farmsolar farm17.6abandoned6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6876, 0.0781).