Energy Projects Near You

Fendyke Solar Farm - Extension (5 MW)

Fendyke Solar Farm - Extension is a 5 MW solar farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 1 November 2016; the record was last updated on 29 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
29 November 2016record last updated
South Hollandcouncil area

Planning timeline

DateStage
12 February 2015Application submitted
11 September 2015Refused by the planning authority
1 December 2015Appeal lodged
1 November 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
29 November 2016
Operator or applicant
BE Renewables/Little Eau Solar
Planning authority
South Holland
Planning application reference
H20-0128-15
Appeal reference
APP/A2525/W/15/3138266
Address (REPD)
New Fendyke House, Fen Dyke, Sutton St. James, Spalding,
Council area (by location)
South Holland
Time to decision
30 weeks
REPD reference
4991

Who decides

ApplicationsSouth HollandUK
Decided applications (solar, wind, battery)4410,236
Refused11 (25%)19%
Solar refused7 of 2612%
Onshore wind refused2 of 345%
Battery storage refused2 of 1516%
Median time from submission to decision13.8 weeks17.0 weeks
Appeals lodged / allowed5 / 6—

UK: all UK planning authorities. Counted under these REPD planning authority names: Lincolnshire, South Holland.

Other large projects within 10 km

ProjectTypeMWStatuskm
Fendyke Solar Farmsolar farm17.6abandoned1.2
Fendyke Farm Solar Farmsolar farm20refused1.5
Fendyke Farmbattery storage10refused1.5
Grange Farm (Lincolnshire)solar farm12.7operational2.8
Treading Wind Farm - Fenlandwind farm15refused on appeal3.3
Treading Wind Farm - South Hollandwind farm5refused3.7
Delph Wind Farmwind farm27application withdrawn3.9
Tydd Solar Farmbattery storage15refused4.9
Tydd Solar Farmsolar farm24.9refused4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7233, 0.0345).