Treading Wind Farm - Fenland (15 MW)

Treading Wind Farm - Fenland is a 15 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 9 October 2013; the record was last updated on 25 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refused on appealstatus in REPD
25 October 2013record last updated
Fenlandcouncil area

Planning timeline

DateStage
21 January 2011Application submitted
3 July 2012Refused by the planning authority
9 October 2013Appeal refused

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused on appeal
Record last updated
25 October 2013
Operator or applicant
Wind Ventures
Planning authority
Fenland
Planning application reference
F/YR11/0113/F
Turbines
6
Address (REPD)
Between Gorefield, Cambs and Sutton St Edmund, Lincs
Council area (by location)
Fenland
Time to decision
76 weeks
REPD reference
3785

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Treading Wind Farm - South Hollandwind farm5refused0.6
Delph Wind Farmwind farm27application withdrawn1.3
Tydd Solar Farmsolar farm24.9refused2.2
Tydd Solar Farmbattery storage15refused2.2
Tydd Solar Farmsolar farm24.9refused2.2
Tydd Solar Farmbattery storage15refused2.2
Fendyke Solar Farm - Extensionsolar farm5refused on appeal3.3
Fendyke Solar Farmsolar farm17.6abandoned4.4
Fendyke Farmbattery storage10refused4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6947, 0.0482).