Tydd Solar Farm (24.9 MW, REPD 16265)

Tydd Solar Farm is a 24.9 MW solar farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 May 2025; the record was last updated on 2 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.9 MWsolar farm
refusedstatus in REPD
2 June 2025record last updated
Fenlandcouncil area

Planning timeline

DateStage
15 April 2024Application submitted
9 May 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
24.9 MW
Status (REPD)
refused
Record last updated
2 June 2025
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Powys
Planning application reference
H19-0329-24
Site area
74.3 ha
Address (REPD)
E/O Guanockgate Road, Sutton St Edmund, Spalding, Wisbech
Council area (by location)
Fenland
Time to decision
56 weeks
REPD reference
16265

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tydd Solar Farmbattery storage15refused<0.1
Tydd Solar Farmsolar farm24.9refused0.1
Tydd Solar Farmbattery storage15refused0.1
Delph Wind Farmwind farm27application withdrawn1.1
Treading Wind Farm - South Hollandwind farm5refused1.6
Treading Wind Farm - Fenlandwind farm15refused on appeal2.2
Fendyke Solar Farm - Extensionsolar farm5refused on appeal5.0
Treading Bank Solar Farmsolar farm49.9refused5.0
Fendyke Solar Farmsolar farm17.6abandoned6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6871, 0.0786).