Fendyke Farm Solar Farm (20 MW)
Fendyke Farm Solar Farm is a 20 MW solar farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 13 May 2025; the record was last updated on 10 June 2025.
20 MWsolar farm
refusedstatus in REPD
10 June 2025record last updated
South Hollandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 2 December 2024 | Application submitted |
| 13 May 2025 | Refused by the planning authority |
Project details
- Technology
- solar farm
- Capacity
- 20 MW
- Status (REPD)
- refused
- Record last updated
- 10 June 2025
- Operator or applicant
- Integrum SPV 21014 Limited
- Planning authority
- South Holland
- Planning application reference
- H20-1007-24
- Site area
- 44.2 ha
- Address (REPD)
- Fendyke Farm, Off Old Fendyke, Sutton St James, Spalding
- Council area (by location)
- South Holland
- Time to decision
- 23 weeks
- Name in REPD
- Fendyke Farm - Solar Farm
- REPD reference
- 17790
Recorded together with Fendyke Farm (10 MW battery storage, refused).
Who decides
| Applications | South Holland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 44 | 10,236 |
| Refused | 11 (25%) | 19% |
| Solar refused | 7 of 26 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 2 of 15 | 16% |
| Median time from submission to decision | 13.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 6 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: Lincolnshire, South Holland.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Fendyke Solar Farm | solar farm | 17.6 | abandoned | 0.4 |
| Fendyke Solar Farm - Extension | solar farm | 5 | refused on appeal | 1.5 |
| Grange Farm (Lincolnshire) | solar farm | 12.7 | operational | 2.2 |
| Treading Wind Farm - Fenland | wind farm | 15 | refused on appeal | 4.8 |
| Treading Wind Farm - South Holland | wind farm | 5 | refused | 5.2 |
| Delph Wind Farm | wind farm | 27 | application withdrawn | 5.3 |
| Treading Bank Solar Farm | solar farm | 49.9 | refused | 6.0 |
| Tydd Solar Farm | battery storage | 15 | refused | 6.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7348, 0.0238).