Cambridge Solar Farm (49.9 MW)

Cambridge Solar Farm is a 49.9 MW solar farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 11 February 2016; the record was last updated on 10 June 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
refusedstatus in REPD
10 June 2019record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
3 July 2015Application submitted
11 February 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
10 June 2019
Operator or applicant
Big 60 Million
Planning authority
South Cambridgeshire
Planning application reference
S/1714/15/FL
Address (REPD)
Land east of Battle Gate Road, St. Neots Road, Dry Drayton, Cambridge
Council area (by location)
South Cambridgeshire
Time to decision
32 weeks
REPD reference
5521

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stargoose Farm Solar Farmsolar farm50approved, not built0.8
Stargoose Farmbattery storage312approved, not built0.8
Bourn Solar Farmsolar farm5refused3.9
Cambridge Wind Farmwind farm32refused on appeal4.4
Skylark Meadow Solar parksolar farm5operational5.6
Falcon Park, Wilsons Road Solar Farm & Battery Energy Storagesolar farm26application submitted6.3
Barton Road, Barton Solar Farmsolar farm5approved, not built8.3
Cantelupe Solar Farmsolar farm5operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2381, -0.0179).