Decoy Farm (5 MW solar farm)

Decoy Farm is a 5 MW solar farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 November 2015; the record was last updated on 18 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 July 2016record last updated
South Hollandcouncil area

Planning timeline

DateStage
29 May 2014Application submitted
13 August 2014Planning permission granted
8 June 2015Construction started
13 November 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 July 2016
Operator or applicant
Push Energy/ NextEnergy Solar Fund (NESF)
Planning authority
South Holland
Planning application reference
H02-0454-14
Address (REPD)
Decoy Farm, Spalding Road, Crowland, Peterborough
Council area (by location)
South Holland
Time to decision
11 weeks
REPD reference
2332

Who decides

ApplicationsSouth HollandUK
Decided applications (solar, wind, battery)4410,236
Refused11 (25%)19%
Solar refused7 of 2612%
Onshore wind refused2 of 345%
Battery storage refused2 of 1516%
Median time from submission to decision13.8 weeks17.0 weeks
Appeals lodged / allowed5 / 6—

UK: all UK planning authorities. Counted under these REPD planning authority names: Lincolnshire, South Holland.

Other large projects within 10 km

ProjectTypeMWStatuskm
French Farm 2 (Extension)wind farm8refused4.1
Hundred Road Wind Turbineswind farm6appeal withdrawn5.1
Farms of Newboroughsolar farm49application withdrawn6.7
Morris Fen (PV)solar farm27application withdrawn6.8
Deeping St Nicholas Wind Farmwind farm16.4operational7.3
Malice Farm, French Drovebattery storage49.9approved, not built7.7
Malice Farm, French Drove Solar Farmsolar farm49.9approved, not built7.7
Nutsgrove Wind Farmwind farm14.4abandoned8.5
Nutsgrove Farm, Thorneysolar farm49.9approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.698, -0.1329).