Malice Farm, French Drove Solar Farm (49.9 MW)

Malice Farm, French Drove Solar Farm is a 49.9 MW solar farm project in Peterborough, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 May 2026, not yet built; the record was last updated on 17 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
17 June 2026record last updated
Peterboroughcouncil area

Planning timeline

DateStage
12 August 2025Application submitted
13 May 2026Planning permission granted
13 May 2031Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
17 June 2026
Operator or applicant
FRV TH Powertek Limited
Planning authority
Peterborough
Planning application reference
25/01028/FUL
Site area
80.4 ha
Address (REPD)
Malice Farm, S/O French Drove And E/O & W/O Scolding Drove, Thorney, Peterborough
Council area (by location)
Peterborough
Time to decision
39 weeks
Name in REPD
Malice Farm, French Drove - Solar Farm
REPD reference
19562

Recorded together with Malice Farm, French Drove (49.9 MW battery storage, approved, not built).

Who decides

ApplicationsPeterboroughUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused0 of 1912%
Onshore wind refused6 of 645%
Battery storage refused0 of 1016%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nutsgrove Wind Farmwind farm14.4abandoned2.2
Nutsgrove Farm, Thorneysolar farm49.9approved, not built2.2
Wryde Croftwind farm26operational2.4
French Farm 2 (Extension)wind farm8refused4.7
Morris Fen (Wind)wind farm16refused5.2
Morris Fen (PV)solar farm27application withdrawn5.3
Treading Wind Farm - Fenlandwind farm15refused on appeal6.4
Treading Wind Farm - South Hollandwind farm5refused6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6642, -0.0326).