Energy Projects Near You

Wryde Croft (26 MW wind farm)

Wryde Croft is a 26 MW wind farm project in Peterborough, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 February 2016; the record was last updated on 15 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWwind farm
operationalstatus in REPD
15 February 2016record last updated
Peterboroughcouncil area

Planning timeline

DateStage
1 July 2006Application submitted
22 October 2008Refused by the planning authority
1 April 2010Planning permission granted
1 April 2010Appeal allowed
1 September 2014Construction started
20 February 2016Operational

Project details

Technology
wind farm
Capacity
26 MW
Status (REPD)
operational
Record last updated
15 February 2016
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Peterborough
Planning application reference
07/01411/FUL
Appeal reference
08/00048/REFPP
Turbines
13
Turbine height
100 m
Address (REPD)
Nutsgrove, South of Thorney.
Council area (by location)
Peterborough
Time to decision
196 weeks
REPD reference
4248

Who decides

ApplicationsPeterboroughUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused0 of 1912%
Onshore wind refused6 of 645%
Battery storage refused0 of 1016%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nutsgrove Farm, Thorneysolar farm49.9approved, not built0.7
Nutsgrove Wind Farmwind farm14.4abandoned0.7
Malice Farm, French Drove Solar Farmsolar farm49.9approved, not built2.4
Malice Farm, French Drovebattery storage49.9approved, not built2.4
Morris Fen (Wind)wind farm16refused3.7
Morris Fen (PV)solar farm27application withdrawn4.6
French Farm 2 (Extension)wind farm8refused5.4
Treading Wind Farm - Fenlandwind farm15refused on appeal8.0
Gores Wind Farmwind farm16application withdrawn8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6422, -0.0323).