Nutsgrove Farm, Thorney (49.9 MW solar farm)

Nutsgrove Farm, Thorney is a 49.9 MW solar farm project in Peterborough, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 June 2024, not yet built; the record was last updated on 16 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
16 July 2024record last updated
Peterboroughcouncil area

Planning timeline

DateStage
27 December 2023Application submitted
28 June 2024Planning permission granted
28 June 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 July 2024
Operator or applicant
Cambridge Power Limited
Planning authority
Peterborough
Planning application reference
23/01746/FUL
Site area
97.4 ha
Address (REPD)
Nutsgrove Farm Scolding Drove Thorney Peterborough Peterborough
Council area (by location)
Peterborough
Time to decision
26 weeks
Name in REPD
Nutsgrove Farm, Thorney - Solar Array
REPD reference
9975

The scheme also includes 50 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsPeterboroughUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused0 of 1912%
Onshore wind refused6 of 645%
Battery storage refused0 of 1016%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nutsgrove Wind Farmwind farm14.4abandoned<0.1
Wryde Croftwind farm26operational0.7
Malice Farm, French Drove Solar Farmsolar farm49.9approved, not built2.2
Malice Farm, French Drovebattery storage49.9approved, not built2.2
Morris Fen (Wind)wind farm16refused3.3
Morris Fen (PV)solar farm27application withdrawn4.0
French Farm 2 (Extension)wind farm8refused4.7
Gores Wind Farmwind farm16application withdrawn7.7
Treading Wind Farm - Fenlandwind farm15refused on appeal8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6449, -0.0415).