Mallard Pass Solar Farm (350 MW)

Mallard Pass Solar Farm is a 350 MW solar farm project in Rutland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 July 2024, not yet built; the record was last updated on 10 March 2025. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010127).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

350 MWsolar farm
approved, not builtstatus in REPD
10 March 2025record last updated
Rutlandcouncil area

Planning timeline

DateStage
24 November 2022Application submitted
12 July 2024Development consent granted (Secretary of State)

Project details

Technology
solar farm
Capacity
350 MW
Status (REPD)
approved, not built
Record last updated
10 March 2025
Operator or applicant
Canadian Solar UK (Recurrent Energy ) / Windel Energy
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010127
Site area
825.0 ha
Address (REPD)
East Coast Main Line, Essendine, Stamford
Council area (by location)
Rutland
Time to decision
85 weeks
REPD reference
9904

Official project record at the Planning Inspectorate (EN010127)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010127). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Home Farm Solar PV Farmsolar farm28approved, not built4.9
Woolfox Quarrysolar farm36.7permission expired8.3
Wittering Ford Road, Barnack Solar Photovoltaic Farmsolar farm11approved, not built8.6
Northorpe Fen Farm, Fen Road Solar Farmsolar farm15approved, not built8.7
Former Woolfox Lodge Airfieldwind farm27refused8.9
Ketton solar farmsolar farm9operational9.0
Deeping Gate Tree Nurseries solar parksolar farm13refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6912, -0.4497).