Energy Projects Near You

Woolfox Quarry (36.7 MW solar farm)

Woolfox Quarry is a 36.7 MW solar farm project in Rutland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 18 March 2019; the record was last updated on 25 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36.7 MWsolar farm
permission expiredstatus in REPD
25 June 2020record last updated
Rutlandcouncil area

Planning timeline

DateStage
13 February 2015Application submitted
18 March 2016Planning permission granted
18 March 2019Permission expired

Project details

Technology
solar farm
Capacity
36.7 MW
Status (REPD)
permission expired
Record last updated
25 June 2020
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Rutland
Planning application reference
2014/1004/MAJ
Site area
64.0 ha
Address (REPD)
Woolfox Quarry, Great North Ro, Stretton, Empingham, Oakham, Leicestershire
Council area (by location)
Rutland
Time to decision
57 weeks
REPD reference
5016

Who decides

ApplicationsRutlandUK
Decided applications (solar, wind, battery)1110,236
Refused1 (9%)19%
Solar refused0 of 912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Former Woolfox Lodge Airfieldwind farm27refused0.7
Ketton solar farmsolar farm9operational7.1
Exton Lane, Burley Solar Farm & Battery Storagesolar farm49.9application submitted7.3
Mallard Pass Solar Farmsolar farm350approved, not built8.3
Home Farm Solar PV Farmsolar farm28approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7077, -0.5696).