Energy Projects Near You

Home Farm Solar PV Farm (28 MW)

Home Farm Solar PV Farm is a 28 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 March 2025, not yet built; the record was last updated on 24 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWsolar farm
approved, not builtstatus in REPD
24 March 2025record last updated
South Kestevencouncil area

Planning timeline

DateStage
10 December 2024Application submitted
13 March 2025Planning permission granted
13 March 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
28 MW
Status (REPD)
approved, not built
Record last updated
24 March 2025
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
South Kesteven
Planning application reference
S24/2100
Site area
54.5 ha
Address (REPD)
Home Farm, Bourne
Council area (by location)
South Kesteven
Time to decision
13 weeks
Name in REPD
Home Farm - Solar PV Farm
REPD reference
16683

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mallard Pass Solar Farmsolar farm350approved, not built4.9
Northorpe Fen Farm, Fen Road Solar Farmsolar farm15approved, not built5.7
Woolfox Quarrysolar farm36.7permission expired9.1
Former Woolfox Lodge Airfieldwind farm27refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7354, -0.4421).