Energy Projects Near You

Solar, wind and battery projects near Stamford (PE9)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE9 (South Kesteven): 6 approved but not yet running, 2 operational. The largest live scheme is Mallard Pass Solar Farm (350 MW solar farm, approved on 12 July 2024, not yet built), 4.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
0awaiting a decision
6approved, not running
2operational

Projects within 10 km of PE9

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Steadfold Lanewind farmwind farm2.6application withdrawnupdated Jul 2012May 2003—Jul 2012North Northamptonshire3.7
Mallard Pass Solar Farmsolar farmsolar farm350approved, not builtupdated Mar 2025Nov 2022granted Jul 2024Mar 2025Rutland4.6
Ketton solar farmsolar farmsolar farm9operationalupdated May 2014Apr 2013granted Jun 2013May 2014Rutland5.4
Ketton solar farm - phase 2solar farmsolar farm3operationalupdated Mar 2015Jan 2014granted Apr 2014Mar 2015Rutland5.4
Land at Wittering Ford Roadsolar farmsolar farm3.9permission expiredupdated Apr 2020Jan 2015granted Jan 2016Apr 2020Peterborough5.5
Wittering Ford Road, Barnack Solar Photovoltaic Farmsolar farmsolar farm11approved, not builtupdated Nov 2023Jul 2023granted Nov 2023Nov 2023Peterborough5.7
Wittering Ford Roadbattery storagebattery storage3approved, not built may be out of dateupdated Dec 2019Sep 2019granted Nov 2019Dec 2019Peterborough6.1
Woolfox Quarrysolar farmsolar farm36.7permission expiredupdated Jun 2020Feb 2015granted Mar 2016Jun 2020Rutland8.4
Former Woolfox Lodge Airfieldwind farmwind farm27refusedupdated Jun 2016Feb 2015refused Dec 2015Jun 2016Rutland8.8
Home Farm Solar PV Farmsolar farmsolar farm28approved, not builtupdated Mar 2025Dec 2024granted Mar 2025Mar 2025South Kesteven9.4
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cherryholt Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2022Jul 2022granted Aug 2022Jul 2022South Kesteven0.7
Morrisonrooftop solarrooftop solar0.7approved, not builtupdated Apr 2022Mar 2022granted Jun 2022Apr 2022South Kesteven1.1

Distance from the average position of the PE9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm70320389
Rooftop solar202000.9
Wind farm200010
Battery storage101003

MW in pipeline: pending, approved and under-construction capacity.

How South Kesteven decides solar, wind and battery applications

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

All projects in South Kesteven

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE9, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.