Former Woolfox Lodge Airfield (27 MW wind farm)

Former Woolfox Lodge Airfield is a 27 MW wind farm project in Rutland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 December 2015; the record was last updated on 28 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWwind farm
refusedstatus in REPD
28 June 2016record last updated
Rutlandcouncil area

Planning timeline

DateStage
9 February 2015Application submitted
16 December 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
27 MW
Status (REPD)
refused
Record last updated
28 June 2016
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Rutland
Planning application reference
2014/1003/MAJ
Turbines
9
Turbine height
130 m
Address (REPD)
Former Woolfox Lodge Airfield, Woolfox Wind Farm, Stretton, Oakham, Leicestershire
Council area (by location)
Rutland
Time to decision
44 weeks
REPD reference
5011

Who decides

ApplicationsRutlandUK
Decided applications (solar, wind, battery)1110,236
Refused1 (9%)19%
Solar refused0 of 912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Woolfox Quarrysolar farm36.7permission expired0.7
Exton Lane, Burley Solar Farm & Battery Storagesolar farm49.9application submitted6.6
Ketton solar farmsolar farm9operational7.0
Mallard Pass Solar Farmsolar farm350approved, not built8.9
Home Farm Solar PV Farmsolar farm28approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7062, -0.5795).