Energy Projects Near You

Renewable energy projects in Rutland

15 solar, wind or battery projects of 150 kW or more are located in Rutland (REPD, July 2026 extract): 1 pending, 8 approved but not running, 3 operational and 1 refused. The council refused 1 of 11 decided applications (9%; UK 19%), with a median 12 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects in the council area
1awaiting a decision
8approved, not running
9%of decisions refused

How Rutland decides

ApplicationsRutlandUK
Decided applications (solar, wind, battery)1110,236
Refused1 (9%)19%
Solar refused0 of 912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Rutland

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Mallard Pass Solar Farmsolar farmsolar farm350approved, not builtupdated Mar 2025Nov 2022granted Jul 2024Mar 2025
Lumiere Solar Farmsolar farmsolar farm50approved, not builtupdated Jun 2026Nov 2024granted May 2026Jun 2026
Exton Lane, Burley Solar Farm & Battery Storagesolar farmsolar farm49.9application submittedupdated Feb 2025Jan 2025—Feb 2025
Pilton Village, Luffenham Lane - Staveley Solar Arraysolar farmsolar farm49.9approved, not builtupdated Feb 2026Mar 2024granted Mar 2025Feb 2026
Woolfox Quarrysolar farmsolar farm36.7permission expiredupdated Jun 2020Feb 2015granted Mar 2016Jun 2020
Ranksborough Farmsolar farmsolar farm28approved, not built may be out of dateupdated Apr 2021Nov 2019granted Jan 2022Apr 2021
Former Woolfox Lodge Airfieldwind farmwind farm27refusedupdated Jun 2016Feb 2015refused Dec 2015Jun 2016
Ketton solar farmsolar farmsolar farm9operationalupdated May 2014Apr 2013granted Jun 2013May 2014
Seaton Road Solar Farmsolar farmsolar farm4operationalupdated Nov 2016Jul 2015granted Sep 2015Nov 2016
Ketton solar farm - phase 2solar farmsolar farm3operationalupdated Mar 2015Jan 2014granted Apr 2014Mar 2015
Hill Top Farmsolar farmsolar farm2.5permission expiredupdated May 2020Aug 2013granted Nov 2013May 2020
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Tesco Stores, South Streetrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Aug 2025granted Oct 2025Dec 2025
Showground Way, Barleythorpe Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025
Rutland Garden Centre, Ashwell Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023
Lumierebattery storagebattery storage—approved, not builtupdated Jun 2026Nov 2024granted May 2026Jun 2026

Postcode districts in Rutland

DistrictProjects within 10 kmPendingApprovedOperational
LE1513173

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Rutland by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.