Pilton Village, Luffenham Lane - Staveley Solar Array (49.9 MW)

Pilton Village, Luffenham Lane - Staveley Solar Array is a 49.9 MW solar farm project in Rutland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 March 2025, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Rutlandcouncil area

Planning timeline

DateStage
13 March 2024Application submitted
27 March 2025Planning permission granted
27 March 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Bluestone Energy Limited
Planning authority
Rutland
Planning application reference
2024/0300/MAF
Site area
80.3 ha
Address (REPD)
South Of Pilton Village Luffenham Lane Pilton
Council area (by location)
Rutland
Time to decision
54 weeks
Contracts for Difference
AR7a
REPD reference
12827

Who decides

ApplicationsRutlandUK
Decided applications (solar, wind, battery)1110,236
Refused1 (9%)19%
Solar refused0 of 912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ketton solar farmsolar farm9operational6.9
Exton Lane, Burley Solar Farm & Battery Storagesolar farm49.9application submitted9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6158, -0.6498).