Washdyke Farm, Billingborough Road Solar farm (27 MW)

Washdyke Farm, Billingborough Road Solar farm is a 27 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 April 2024, not yet built; the record was last updated on 23 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWsolar farm
approved, not builtstatus in REPD
23 February 2026record last updated
South Kestevencouncil area

Planning timeline

DateStage
27 March 2023Application submitted
28 July 2023Refused by the planning authority
23 April 2024Planning permission granted
23 April 2024Appeal refused
23 April 2024Appeal allowed
23 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
27 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
GS Ignis Limited
Planning authority
South Kesteven
Planning application reference
S23/0511
Appeal reference
APP/E2530/W/24/3337544
Site area
26.0 ha
Address (REPD)
Washdyke Farm, Billingborough Road, Folkingham, Sleaford
Council area (by location)
South Kesteven
Time to decision
56 weeks
Contracts for Difference
AR7a
Name in REPD
Washdyke Farm, Billingborough Road - Solar farm
REPD reference
12419

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
White Gorse Farmsolar farm11.6permission expired5.9
Neslam Wind Farmwind farm12application withdrawn7.2
Gorse Lanesolar farm20under construction8.7
Burton Gorse Plantation, Whitecross Lanesolar farm42application submitted8.8
Grange Farm (Burton Pedwardine)solar farm15operational9.3
White Cross Lanesolar farm25under construction9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8914, -0.3922).