Energy Projects Near You

Gorse Lane (20 MW solar farm)

Gorse Lane is a 20 MW solar farm project in North Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2021; the record was last updated on 17 May 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
under constructionstatus in REPD
17 May 2022record last updated
North Kestevencouncil area

Planning timeline

DateStage
15 January 2019Application submitted
29 March 2019Planning permission granted
1 May 2021Construction started

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
under construction
Record last updated
17 May 2022
Operator or applicant
Elgin Energy Esco
Planning authority
North Kesteven
Planning application reference
19/0060/FUL
Site area
67.6 ha
Address (REPD)
Land South Of, Gorse Lane, Silk Willoughby, Sleaford,
Council area (by location)
North Kesteven
Time to decision
10 weeks
REPD reference
6701

Who decides

ApplicationsNorth KestevenUK
Decided applications (solar, wind, battery)3510,236
Refused3 (9%)19%
Solar refused2 of 2912%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mareham Lane, Solar PV Panelssolar farm50approved, not built2.7
White Cross Lanesolar farm25under construction3.3
Burton Gorse Plantation, Whitecross Lanesolar farm42application submitted3.3
Beacon Fen Energy Parksolar farm400application submitted3.4
Grange Farm (Burton Pedwardine)solar farm15operational3.9
White Gorse Farmsolar farm11.6permission expired4.4
Deepdale Farmsolar farm8operational6.7
Ewerby Thorpe Farmsolar farm25abandoned8.4
Washdyke Farm, Billingborough Road Solar farmsolar farm27approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9682, -0.4133).