Grange Farm (Burton Pedwardine) (15 MW solar farm)
Grange Farm (Burton Pedwardine) is a 15 MW solar farm project in North Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 April 2014; the record was last updated on 10 June 2014.
15 MWsolar farm
operationalstatus in REPD
10 June 2014record last updated
North Kestevencouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 November 2012 | Application submitted |
| 4 February 2013 | Planning permission granted |
| 10 June 2013 | Construction started |
| 30 April 2014 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 15 MW
- Status (REPD)
- operational
- Record last updated
- 10 June 2014
- Operator or applicant
- Lark Energy
- Planning authority
- North Kesteven
- Planning application reference
- 12/1242/FUL
- Site area
- 28.9 ha
- Address (REPD)
- Asgarby Road, Burton Pedwardine, Lincoln
- Council area (by location)
- North Kesteven
- Time to decision
- 10 weeks
- REPD reference
- 1755
Who decides
| Applications | North Kesteven | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 35 | 10,236 |
| Refused | 3 (9%) | 19% |
| Solar refused | 2 of 29 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 10.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Burton Gorse Plantation, Whitecross Lane | solar farm | 42 | application submitted | 0.7 |
| White Cross Lane | solar farm | 25 | under construction | 0.8 |
| White Gorse Farm | solar farm | 11.6 | permission expired | 3.4 |
| Mareham Lane, Solar PV Panels | solar farm | 50 | approved, not built | 3.8 |
| Gorse Lane | solar farm | 20 | under construction | 3.9 |
| Beacon Fen Energy Park | solar farm | 400 | application submitted | 4.7 |
| Ewerby Thorpe Farm | solar farm | 25 | abandoned | 5.4 |
| Deepdale Farm | solar farm | 8 | operational | 6.8 |
| Little Hale Drove, Little Hale Fen | battery storage | 99 | approved, not built | 6.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9722, -0.3555).