Little Hale Drove, Little Hale Fen (99 MW battery storage)

Little Hale Drove, Little Hale Fen is a 99 MW battery storage project in North Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 March 2025, not yet built; the record was last updated on 4 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
approved, not builtstatus in REPD
4 April 2025record last updated
North Kestevencouncil area

Planning timeline

DateStage
8 November 2024Application submitted
14 March 2025Planning permission granted
14 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
approved, not built
Record last updated
4 April 2025
Operator or applicant
Root-Power (South) Limited
Planning authority
North Kesteven
Planning application reference
24/1265/FUL
Address (REPD)
Lying To The South Of Little Hale Drove Little Hale Fen
Council area (by location)
North Kesteven
Time to decision
18 weeks
Name in REPD
Little Hale Drove, Little Hale Fen - Battery Storage
REPD reference
17585

Who decides

ApplicationsNorth KestevenUK
Decided applications (solar, wind, battery)3510,236
Refused3 (9%)19%
Solar refused2 of 2912%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Hale Fen Solar Farmsolar farm50approved, not built0.8
Bicker Fenwind farm26.7operational3.1
Vicarage Drove Solar farm & Battery storagesolar farm49.9approved, not built3.2
Bicker Drovebattery storage100approved, not built4.0
Cowbridge Road, Bicker Fensolar farm75under construction4.4
Bicker Fen Bess, Vicarage Drovebattery storage400approved, not built4.7
Heckington Fen Solar Parksolar farm500approved, not built4.8
Heckington Fenswind farm54permission expired6.3
Grange Farm (Burton Pedwardine)solar farm15operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9477, -0.2616).