Heckington Fens (54 MW wind farm)

Heckington Fens is a 54 MW wind farm project in North Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 8 February 2018; the record was last updated on 3 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54 MWwind farm
permission expiredstatus in REPD
3 August 2020record last updated
North Kestevencouncil area

Planning timeline

DateStage
16 December 2009Application submitted
8 February 2013Planning permission granted
8 February 2018Permission expired

Project details

Technology
wind farm
Capacity
54 MW
Status (REPD)
permission expired
Record last updated
3 August 2020
Operator or applicant
Ecotricity
Planning authority
North Kesteven
Planning application reference
S36
Turbines
22
Turbine height
125 m
Address (REPD)
East Heckington, North Kesteven, Lincolnshire
Council area (by location)
North Kesteven
Time to decision
164 weeks
REPD reference
4147

Who decides

ApplicationsNorth KestevenUK
Decided applications (solar, wind, battery)3510,236
Refused3 (9%)19%
Solar refused2 of 2912%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Heckington Fen Solar Parksolar farm500approved, not built3.2
Ewerby Thorpe Farmsolar farm25abandoned5.8
Little Hale Drove, Little Hale Fenbattery storage99approved, not built6.3
Little Hale Fen Solar Farmsolar farm50approved, not built6.8
Bicker Drovebattery storage100approved, not built7.1
Bicker Fenwind farm26.7operational7.1
Vicarage Drove Solar farm & Battery storagesolar farm49.9approved, not built7.8
Bicker Fen Bess, Vicarage Drovebattery storage400approved, not built8.4
Cowbridge Road, Bicker Fensolar farm75under construction8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0012, -0.2314).