Ewerby Thorpe Farm (25 MW solar farm)

Ewerby Thorpe Farm is a 25 MW solar farm project in North Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 25 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
abandonedstatus in REPD
25 October 2017record last updated
North Kestevencouncil area

Planning timeline

DateStage
7 August 2014Application submitted
3 October 2014Planning permission granted
3 October 2017Permission expired

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
abandoned
Record last updated
25 October 2017
Operator or applicant
Estover Energy
Planning authority
North Kesteven
Planning application reference
14/1003/FUL
Site area
53.9 ha
Address (REPD)
Ewerby Thorpe Farm, Ewerby Thorpe, Sleaford, Lincolnshire, NG34 9PR
Council area (by location)
North Kesteven
Time to decision
8 weeks
REPD reference
2209

Who decides

ApplicationsNorth KestevenUK
Decided applications (solar, wind, battery)3510,236
Refused3 (9%)19%
Solar refused2 of 2912%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grange Farm (Burton Pedwardine)solar farm15operational5.4
White Cross Lanesolar farm25under construction5.5
Heckington Fenswind farm54permission expired5.8
Deepdale Farmsolar farm8operational5.8
Burton Gorse Plantation, Whitecross Lanesolar farm42application submitted6.1
Mareham Lane, Solar PV Panelssolar farm50approved, not built6.4
Beacon Fen Energy Parksolar farm400application submitted6.6
Little Hale Drove, Little Hale Fenbattery storage99approved, not built8.2
Heckington Fen Solar Parksolar farm500approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0145, -0.3145).