Energy Projects Near You

Bicker Fen Bess, Vicarage Drove (400 MW)

Bicker Fen Bess, Vicarage Drove is a 400 MW battery storage project in Boston, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 February 2025, not yet built; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
12 May 2025record last updated
Bostoncouncil area

Planning timeline

DateStage
10 October 2024Application submitted
5 February 2025Planning permission granted
5 February 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
12 May 2025
Operator or applicant
FRV TH Powertek Limited
Planning authority
Boston
Planning application reference
B/24/0415
Address (REPD)
Bicker Fen BESS, Land off Vicarage Drove, Bicker Fen
Council area (by location)
Boston
Time to decision
17 weeks
Name in REPD
Bicker Fen Bess, Vicarage Drove - Battery Storage
REPD reference
16628

Who decides

ApplicationsBostonUK
Decided applications (solar, wind, battery)1910,236
Refused1 (5%)19%
Solar refused1 of 1412%
Onshore wind refused0 of 145%
Battery storage refused0 of 416%
Median time from submission to decision14.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cowbridge Road, Bicker Fensolar farm75under construction1.0
Bicker Drovebattery storage100approved, not built1.3
Vicarage Drove Solar farm & Battery storagesolar farm49.9approved, not built1.5
Bicker Fenwind farm26.7operational1.6
Little Hale Fen Solar Farmsolar farm50approved, not built4.0
Little Hale Drove, Little Hale Fenbattery storage99approved, not built4.7
Heckington Fen Solar Parksolar farm500approved, not built5.4
Nowhere Farmsolar farm8.1operational6.3
Neslam Wind Farmwind farm12application withdrawn7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9282, -0.2001).