Energy Projects Near You

Vicarage Drove Solar farm & Battery storage (49.9 MW)

Vicarage Drove Solar farm & Battery storage is a 49.9 MW solar farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 January 2024, not yet built; the record was last updated on 11 March 2025. REPD also records that the planning permission expired on 17 February 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
11 March 2025record last updated
South Hollandcouncil area

REPD also records that the planning permission expired on 17 February 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
5 October 2021Application submitted
23 January 2024Planning permission granted
17 February 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
11 March 2025
Operator or applicant
Renewable Connections Developments Limited
Planning authority
Boston
Planning application reference
B/21/0443
Site area
80.5 ha
Address (REPD)
Land at Vicarage Drove, Bicker, Boston
Council area (by location)
South Holland
Time to decision
120 weeks
Name in REPD
Vicarage Drove - Solar farm & Battery storage
REPD reference
8517

The scheme also includes 20.5 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsBostonUK
Decided applications (solar, wind, battery)1910,236
Refused1 (5%)19%
Solar refused1 of 1412%
Onshore wind refused0 of 145%
Battery storage refused0 of 416%
Median time from submission to decision14.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bicker Fenwind farm26.7operational0.8
Cowbridge Road, Bicker Fensolar farm75under construction1.2
Bicker Fen Bess, Vicarage Drovebattery storage400approved, not built1.5
Bicker Drovebattery storage100approved, not built1.6
Little Hale Fen Solar Farmsolar farm50approved, not built2.5
Little Hale Drove, Little Hale Fenbattery storage99approved, not built3.2
Heckington Fen Solar Parksolar farm500approved, not built5.2
Neslam Wind Farmwind farm12application withdrawn6.9
Heckington Fenswind farm54permission expired7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.931, -0.2226).