Welbeck Colliery (11.3 MW solar farm)

Welbeck Colliery is an 11.3 MW solar farm project in Mansfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 July 2014; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.3 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Mansfieldcouncil area

Planning timeline

DateStage
21 November 2012Application submitted
11 February 2013Planning permission granted
15 March 2014Construction started
25 July 2014Operational

Project details

Technology
solar farm
Capacity
11.3 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Mansfield
Planning application reference
2012/0557/NT
Site area
23.1 ha
Address (REPD)
Elkesley Road, Meden Vale, Mansfield, Nottinghamshire
Council area (by location)
Mansfield
Time to decision
12 weeks
REPD reference
2283

Who decides

ApplicationsMansfieldUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused3 of 1412%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brecks Solar Farmsolar farm45.4approved, not built2.4
Welbeck Solar / Hazel Gapsolar farm16operational2.7
Netherfield Lanesolar farm19.7operational3.2
Land West Of Sookholme Roadsolar farm10refused4.6
Hunciecroft Farmsolar farm8operational5.2
Creswell Solar Parksolar farm5operational5.8
Frithwood Farm, Frithwood Lane Solar Farmsolar farm25approved, not built6.4
Littlewood Lane Solarsolar farm5operational6.5
Land at Bolsover Moor Quarrysolar farm5operational8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2239, -1.1377).