Energy Projects Near You

Creswell Solar Park (5 MW)

Creswell Solar Park is a 5 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 16 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 January 2017record last updated
Bassetlawcouncil area

Planning timeline

DateStage
20 April 2015Application submitted
3 July 2015Planning permission granted
19 February 2016Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 January 2017
Operator or applicant
Sovereign Energy Partners
Planning authority
Bolsover
Planning application reference
15/00173/FUL
Site area
11.8 ha
Address (REPD)
Land To The North And, Frithwo, Elmton, South Of Sewage Treatment Plan, Worksop,
Council area (by location)
Bassetlaw
Time to decision
11 weeks
REPD reference
5224

Earlier applications for this site

ApplicationMWSubmittedOutcome
Moneystone Quarry SMD/2014/04328.528 June 2014refused 5 March 2015
Creswell 14/00349/FUL57 August 2014replaced by a revised application

Who decides

ApplicationsBolsoverUK
Decided applications (solar, wind, battery)2010,236
Refused4 (20%)19%
Solar refused2 of 1212%
Onshore wind refused2 of 245%
Battery storage refused0 of 616%
Median time from submission to decision12.5 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hunciecroft Farmsolar farm8operational1.4
Frithwood Farm, Frithwood Lane Solar Farmsolar farm25approved, not built1.5
Land at Bolsover Moor Quarrysolar farm5operational3.6
Steeley Lane, Steetley Solar Photovoltaic Farmsolar farm18.7application submitted5.4
Welbeck Collierysolar farm11.3operational5.8
Brecks Solar Farmsolar farm45.4approved, not built6.7
Welbeck Solar / Hazel Gapsolar farm16operational6.8
Land West Of Sookholme Roadsolar farm10refused7.1
Roseland Community Wind Farmwind farm12refused7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2558, -1.2074).