Wood Lane Solar Farm (49.9 MW)

Wood Lane Solar Farm is a 49.9 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 August 2020, not yet built; the record was last updated on 18 November 2024. REPD records the planning permission as expiring on 2 March 2025, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
18 November 2024record last updated
Bassetlawcouncil area

REPD records the planning permission as expiring on 2 March 2025, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
6 February 2020Application submitted
27 August 2020Planning permission granted
2 March 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
18 November 2024
Operator or applicant
Scottish Power Limited
Planning authority
Bassetlaw
Planning application reference
20/00117/FUL
Site area
95.3 ha
Address (REPD)
Land North West And South Of F, Wood Lane, Sturton-le-Steeple, Retford, Nottinghamshire
Council area (by location)
Bassetlaw
Time to decision
29 weeks
Contracts for Difference
AR4
REPD reference
7786

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Steeple Renewables Projectsolar farm450application submitted2.9
West Burton Power Station, North Roadbattery storage500approved, not built2.9
West Burtonbattery storage49operational4.0
Gainsborough Road, Saundby Solar Farmsolar farm78under construction4.4
Gainsborough Road, Saundbybattery storage120under construction4.4
Crow Holt Windfarmwind farm20refused5.0
Chainbridge Roadsolar8application withdrawn5.0
Tiln Farm solar parksolar farm8operational5.1
West End Farm - Treswellsolar farm16.9abandoned5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3478, -0.8523).