West End Farm - Treswell (16.9 MW solar farm)
West End Farm - Treswell is a 16.9 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 22 December 2015.
16.9 MWsolar farm
abandonedstatus in REPD
22 December 2015record last updated
Bassetlawcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 9 September 2014 | Application submitted |
| 27 February 2015 | Planning permission granted |
| 27 February 2018 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 16.9 MW
- Status (REPD)
- abandoned
- Record last updated
- 22 December 2015
- Operator or applicant
- Kinetica Solar
- Planning authority
- Bassetlaw
- Planning application reference
- 14/00989/FUL
- Site area
- 22.0 ha
- Address (REPD)
- Land East Of Ashley Lane Treswell Nottinghamshire
- Council area (by location)
- Bassetlaw
- Time to decision
- 24 weeks
- REPD reference
- 1313
Who decides
| Applications | Bassetlaw | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 40 | 10,236 |
| Refused | 5 (12%) | 19% |
| Solar refused | 0 of 25 | 12% |
| Onshore wind refused | 5 of 7 | 45% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 13.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Crow Holt Windfarm | wind farm | 20 | refused | 2.3 |
| Torksey Ferry Road, Rampton | battery storage | 500 | approved, not built | 2.6 |
| Drayton Road, Upton Solar Farm | solar farm | 49.9 | application submitted | 3.1 |
| Long Ridding Lane, East Drayton Solar Farm | solar farm | 49.9 | application submitted | 3.5 |
| Cottom Power Station | battery storage | 50 | application submitted | 3.8 |
| Cottam Power Station | battery storage | 49 | approved, not built | 3.9 |
| Cottam wind farm | wind farm | 6.9 | application withdrawn | 4.2 |
| Wood Lane Solar Farm | solar farm | 49.9 | approved, not built | 5.2 |
| Marton Sewage Works, High Street | battery storage | 10 | application submitted | 6.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3019, -0.8379).