Energy Projects Near You

Cottom Power Station (50 MW battery storage)

Cottom Power Station is a 50 MW battery storage project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 13 October 2020, no decision recorded; the record was last updated on 12 January 2021. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
application submittedmay be out of datestatus in REPD
12 January 2021record last updated
Bassetlawcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
13 October 2020Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
application submitted
Record last updated
12 January 2021
Operator or applicant
EDF Energy Thermal Generation Limited
Planning authority
Bassetlaw
Planning application reference
20/01288/CTP
Address (REPD)
Cottam Power Station
Council area (by location)
Bassetlaw
REPD reference
8278

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cottam Power Stationbattery storage49approved, not built0.4
Torksey Ferry Road, Ramptonbattery storage500approved, not built1.4
Cottam wind farmwind farm6.9application withdrawn2.2
Marton Sewage Works, High Streetbattery storage10application submitted3.5
West End Farm - Treswellsolar farm16.9abandoned3.8
Gate Burton Solar & Energy Storage Parksolar farm531approved, not built4.5
Stow Park Farm, Stow Parksolar farm35application submitted4.9
Long Ridding Lane, East Drayton Solar Farmsolar farm49.9application submitted5.3
Danes Farm - extensionsolar farm10.5operational6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3034, -0.7815).