Gate Burton Solar & Energy Storage Park (531 MW)

Gate Burton Solar & Energy Storage Park is a 531 MW solar farm project in West Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 July 2024, not yet built; the record was last updated on 16 December 2024. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010131).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

531 MWsolar farm
approved, not builtstatus in REPD
16 December 2024record last updated
West Lindseycouncil area

Planning timeline

DateStage
27 January 2023Application submitted
12 July 2024Development consent granted (Secretary of State)

Project details

Technology
solar farm
Capacity
531 MW
Status (REPD)
approved, not built
Record last updated
16 December 2024
Operator or applicant
Low Carbon
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010131
Address (REPD)
Gate Burton, Knaith Park & Willingham-by-Stow, Gainsborough
Council area (by location)
West Lindsey
Time to decision
76 weeks
Name in REPD
Gate Burton - Solar & Energy Storage Park
REPD reference
9809

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010131)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010131). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Marton Sewage Works, High Streetbattery storage10application submitted1.6
Stow Park Farm, Stow Parksolar farm35application submitted2.6
Cottam wind farmwind farm6.9application withdrawn3.2
Danes Farm - extensionsolar farm10.5operational3.4
Cottom Power Stationbattery storage50application submitted4.5
Cottam Power Stationbattery storage49approved, not built4.7
West Burtonbattery storage49operational4.9
Torksey Ferry Road, Ramptonbattery storage500approved, not built5.7
Steeple Renewables Projectsolar farm450application submitted6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.336, -0.7426).