Tiln Farm solar park (8 MW)

Tiln Farm solar park is an 8 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 19 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
19 June 2015record last updated
Bassetlawcouncil area

Planning timeline

DateStage
27 September 2013Application submitted
20 December 2013Planning permission granted
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
19 June 2015
Operator or applicant
Pfalz Solar
Planning authority
Bassetlaw
Planning application reference
13/00997/FUL
Site area
22.0 ha
Address (REPD)
Land East Of Tiln Farm Tiln Lane Retford Nottinghamshire
Council area (by location)
Bassetlaw
Time to decision
12 weeks
REPD reference
2356

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tiln Farm Solar Farmsolar farm49.9under construction0.9
Chainbridge Roadsolar8application withdrawn2.3
Bellmoor Grasslandsolar5abandoned2.7
Wood Lane Solar Farmsolar farm49.9approved, not built5.1
Crow Holt Windfarmwind farm20refused6.0
Walkers Wood Solar Parksolar farm27operational6.0
Little Morton Solar Farmsolar farm14.3operational6.4
Jubilee Farm, Barnby Moorsolar farm5operational7.2
Steeple Renewables Projectsolar farm450application submitted7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3468, -0.9294).