Energy Projects Near You

Bellmoor Grassland (5 MW solar)

Bellmoor Grassland is a 5 MW solar project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 18 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar
abandonedstatus in REPD
18 December 2015record last updated
Bassetlawcouncil area

Planning timeline

DateStage
8 October 2013Application submitted
21 December 2013Planning permission granted
21 December 2021Permission expired

Project details

Technology
solar
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
18 December 2015
Operator or applicant
Fred Walter & Sons Ltd
Planning authority
Bassetlaw
Planning application reference
13/01126/FUL
Address (REPD)
Land At Bellmoor Grassland Sutton Cum Lound Retford Notts
Council area (by location)
Bassetlaw
Time to decision
11 weeks
REPD reference
1911

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tiln Farm Solar Farmsolar farm49.9under construction1.8
Tiln Farm solar parksolar farm8operational2.7
Chainbridge Roadsolar8application withdrawn3.8
Walkers Wood Solar Parksolar farm27operational4.5
Jubilee Farm, Barnby Moorsolar farm5operational4.6
Little Morton Solar Farmsolar farm14.3operational5.3
Elkesley Southbound, Elkesleybattery storage480application submitted7.6
Wood Lane Solar Farmsolar farm49.9approved, not built7.8
Crow Holt Windfarmwind farm20refused8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.349, -0.9694).