Energy Projects Near You

Chainbridge Road (8 MW solar)

Chainbridge Road is an 8 MW solar project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 14 August 2014; the record was last updated on 16 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar
application withdrawnstatus in REPD
16 September 2014record last updated
Bassetlawcouncil area

Planning timeline

DateStage
29 January 2014Application submitted
14 August 2014Application withdrawn

Project details

Technology
solar
Capacity
8 MW
Status (REPD)
application withdrawn
Record last updated
16 September 2014
Operator or applicant
Temporis Capital
Planning authority
Bassetlaw
Planning application reference
14/00087/FUL
Address (REPD)
Land 1 Chainbridge Road Lound Nottinghamshire
Council area (by location)
Bassetlaw
REPD reference
2297

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tiln Farm solar parksolar farm8operational2.3
Tiln Farm Solar Farmsolar farm49.9under construction2.8
Bellmoor Grasslandsolar5abandoned3.8
Wood Lane Solar Farmsolar farm49.9approved, not built5.0
Steeple Renewables Projectsolar farm450application submitted6.7
West Burton Power Station, North Roadbattery storage500approved, not built6.7
Gainsborough Road, Saundby Solar Farmsolar farm78under construction6.8
Gainsborough Road, Saundbybattery storage120under construction6.8
Jubilee Farm, Barnby Moorsolar farm5operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3671, -0.9208).