Chainbridge Road (8 MW solar)
Chainbridge Road is an 8 MW solar project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 14 August 2014; the record was last updated on 16 September 2014.
8 MWsolar
application withdrawnstatus in REPD
16 September 2014record last updated
Bassetlawcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 January 2014 | Application submitted |
| 14 August 2014 | Application withdrawn |
Project details
- Technology
- solar
- Capacity
- 8 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 16 September 2014
- Operator or applicant
- Temporis Capital
- Planning authority
- Bassetlaw
- Planning application reference
- 14/00087/FUL
- Address (REPD)
- Land 1 Chainbridge Road Lound Nottinghamshire
- Council area (by location)
- Bassetlaw
- REPD reference
- 2297
Who decides
| Applications | Bassetlaw | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 40 | 10,236 |
| Refused | 5 (12%) | 19% |
| Solar refused | 0 of 25 | 12% |
| Onshore wind refused | 5 of 7 | 45% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 13.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Tiln Farm solar park | solar farm | 8 | operational | 2.3 |
| Tiln Farm Solar Farm | solar farm | 49.9 | under construction | 2.8 |
| Bellmoor Grassland | solar | 5 | abandoned | 3.8 |
| Wood Lane Solar Farm | solar farm | 49.9 | approved, not built | 5.0 |
| Steeple Renewables Project | solar farm | 450 | application submitted | 6.7 |
| West Burton Power Station, North Road | battery storage | 500 | approved, not built | 6.7 |
| Gainsborough Road, Saundby Solar Farm | solar farm | 78 | under construction | 6.8 |
| Gainsborough Road, Saundby | battery storage | 120 | under construction | 6.8 |
| Jubilee Farm, Barnby Moor | solar farm | 5 | operational | 7.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3671, -0.9208).