Energy Projects Near You

Solar, wind and battery projects near Doncaster (DN10)

21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN10 (Bassetlaw): 3 are waiting for a planning decision, 7 approved but not yet running, 5 operational. The largest live scheme is West Burton Power Station, North Road (500 MW battery storage, approved on 5 September 2024, not yet built), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21projects within 10 km
3awaiting a decision
7approved, not running
5operational

Projects within 10 km of DN10

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Misson Solar Farmsolar farmsolar farm5operationalupdated Jul 2016Feb 2015granted Oct 2015Jul 2016Bassetlaw4.0
Chainbridge Roadsolarsolar8application withdrawnupdated Sep 2014Jan 2014—Sep 2014Bassetlaw6.4
Partridge Hill Solar Farmsolar farmsolar farm33approved, not built may be out of dateupdated Mar 2020May 2015granted Jul 2016Mar 2020Doncaster6.9
Tiln Farm Retford (extension)solar farmsolar farm1.7operationalupdated Jul 2016Mar 2015granted Jun 2015Jul 2016Bassetlaw8.5
Barnby Moorsolar farmsolar farm4operationalupdated Aug 2015Nov 2013granted Feb 2014Aug 2015Bassetlaw8.6
Tiln Farm solar parksolar farmsolar farm8operationalupdated Jun 2015Sep 2013granted Dec 2013Jun 2015Bassetlaw8.6
Old Trent Road, Beckinghambattery storagebattery storage80application withdrawnupdated Mar 2025Sep 2023—Mar 2025Bassetlaw8.6
Gainsborough Road, Saundbybattery storagebattery storage120under constructionupdated Jun 2026Mar 2022granted Jul 2022Jun 2026Bassetlaw8.7
Gainsborough Road, Saundby Solar Farmsolar farmsolar farm78under constructionupdated Jun 2026Mar 2022granted Jul 2022Jun 2026Bassetlaw8.7
Bellmoor Grasslandsolarsolar5abandonedupdated Dec 2015Oct 2013granted Dec 2013Dec 2015Bassetlaw8.7
Tiln Farm Solar Farmsolar farmsolar farm49.9under constructionupdated Nov 2022Nov 2020granted Sep 2023Nov 2022Bassetlaw8.8
Babworth Estatewind farmwind farm1refusedupdated Jun 2014Mar 2014refused May 2014Jun 2014Bassetlaw8.9
Smeath Road Wind Turbineswind farmwind farm1refused on appealupdated Apr 2016Jul 2014refused Jul 2015Apr 2016Bassetlaw8.9
Jubilee Farm, Barnby Moorsolar farmsolar farm5operationalupdated Jul 2017Jul 2014granted Jan 2015Jul 2017Bassetlaw9.3
Saundby Wind Farmwind farmwind farm15application withdrawnupdated Sep 2015May 2014—Sep 2015West Lindsey9.8
West Burton Power Station, North Roadbattery storagebattery storage500approved, not builtupdated Sep 2024Dec 2022granted Sep 2024Sep 2024Bassetlaw10.0
Steeple Renewables Projectsolar farmsolar farm450application submittedupdated Oct 2025May 2025—Oct 2025Bassetlaw10.0
Steeple Renewables Projectbattery storagebattery storage150application submittedupdated Oct 2025May 2025—Oct 2025Bassetlaw10.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Misterton PSD, Stockwith Roadsolar farmsolar farm0.4approved, not builtupdated Mar 2024Dec 2023granted Feb 2024Mar 2024Bassetlaw6.6
Butternut Box, Symmetry Parkrooftop solarrooftop solar0.7application submittedupdated May 2026Dec 2025—May 2026Bassetlaw9.3
Linroyal Potato Processing Plant, Heckdykerooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Feb 2023Mar 2023North Lincolnshire9.5

Distance from the average position of the DN10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101450611
Rooftop solar211001
Solar200000
Wind farm300020
Battery storage41200770

MW in pipeline: pending, approved and under-construction capacity.

How Bassetlaw decides solar, wind and battery applications

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Bassetlaw

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN10, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.