Energy Projects Near You

Gainsborough Road, Saundby (120 MW battery storage)

Gainsborough Road, Saundby is a 120 MW battery storage project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2026; the record was last updated on 8 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

120 MWbattery storage
under constructionstatus in REPD
8 June 2026record last updated
Bassetlawcouncil area

Planning timeline

DateStage
17 March 2022Application submitted
14 July 2022Planning permission granted
1 June 2026Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
120 MW
Status (REPD)
under construction
Record last updated
8 June 2026
Operator or applicant
Enso Energy / Cero Generation
Planning authority
Bassetlaw
Planning application reference
22/00358/FUL
Address (REPD)
E/O Bumble Bee Farm, Saundby Road, Gainsborough Road, Saundby
Council area (by location)
Bassetlaw
Time to decision
17 weeks
Name in REPD
Gainsborough Road, Saundby - Battery Storage Facility
REPD reference
9816

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gainsborough Road, Saundby Solar Farmsolar farm78under construction<0.1
Saundby Wind Farmwind farm15application withdrawn1.7
Steeple Renewables Projectsolar farm450application submitted2.0
West Burton Power Station, North Roadbattery storage500approved, not built2.0
West Burtonbattery storage49operational2.6
Old Trent Road, Beckinghambattery storage80application withdrawn2.8
Wood Lane Solar Farmsolar farm49.9approved, not built4.4
Chainbridge Roadsolar8application withdrawn6.8
Cottam wind farmwind farm6.9application withdrawn7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3829, -0.8221).