Manton Manor Solar Farm (27 MW)

Manton Manor Solar Farm is a 27 MW solar farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 28 June 2016; the record was last updated on 1 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWsolar farm
refused on appealstatus in REPD
1 July 2016record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
17 April 2015Application submitted
18 November 2015Refused by the planning authority
2 March 2016Appeal lodged
28 June 2016Appeal refused

Project details

Technology
solar farm
Capacity
27 MW
Status (REPD)
refused on appeal
Record last updated
1 July 2016
Operator or applicant
Pegasus Group
Planning authority
North Lincolnshire
Planning application reference
PA/2015/0387
Appeal reference
APP/Y2003/W/16/3144447
Address (REPD)
Manor Farm, Access Roads In Ma, Manton, Gainsborough, Lincolnshire
Council area (by location)
North Lincolnshire
Time to decision
31 weeks
REPD reference
5161

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sand Lane Solar Farmsolar farm20.2application submitted1.8
Raventhorpe Lodge (Sweeting Thorns)solar farm25permission expired4.4
Raventhorpe Farmsolar farm38operational5.0
Little Crow Solar Parksolar farm150approved, not built6.5
Scawby Brook, Briggbattery storage99approved, not built7.2
Scawby Roadsolar farm49.9application submitted7.7
Laughton Wind Farmwind farm28refused on appeal8.3
Winterton Roadbattery storage95approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5181, -0.607).