Laughton Wind Farm (28 MW)

Laughton Wind Farm is a 28 MW wind farm project in West Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 17 April 2008; the record was last updated on 11 December 2008.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWwind farm
refused on appealstatus in REPD
11 December 2008record last updated
West Lindseycouncil area

Planning timeline

DateStage
21 March 2006Application submitted
29 November 2007Refused by the planning authority
17 April 2008Appeal refused

Project details

Technology
wind farm
Capacity
28 MW
Status (REPD)
refused on appeal
Record last updated
11 December 2008
Operator or applicant
Laughton Wind Farm
Planning authority
West Lindsey
Planning application reference
M06/P/0280
Appeal reference
APP/N2535/A/07/2048474/NWF
Turbines
8
Address (REPD)
Mount Pleasant Farm , Scotton Rd , (1km east of Laughton and 8km northeast of the centre of Gainsborough) , Loughton
Council area (by location)
West Lindsey
Time to decision
88 weeks
REPD reference
3001

Earlier applications for this site

ApplicationMWSubmittedOutcome
Laughton Wind Farm M03/P/1152163 November 2003refused 25 August 2004

Who decides

ApplicationsWest LindseyUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused3 of 2112%
Onshore wind refused3 of 345%
Battery storage refused1 of 216%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brown's Holt Wind Farmwind farm24application withdrawn5.7
Sand Lane Solar Farmsolar farm20.2application submitted6.8
Manton Manor Solar Farmsolar farm27refused on appeal8.3
Solar Panels at Tillbridge Solar Farmsolar farm500approved, not built8.5
Hemswell Cliff Wind Farmwind farm25refused on appeal9.8
Old Trent Road, Beckinghambattery storage80application withdrawn9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4626, -0.6911).