Saxby Wold Wind Farm (36 MW)

Saxby Wold Wind Farm is a 36 MW wind farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 1 August 2014; the record was last updated on 5 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
refused on appealstatus in REPD
5 September 2014record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
21 June 2011Application submitted
8 February 2012Refused by the planning authority
1 August 2014Appeal refused

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
refused on appeal
Record last updated
5 September 2014
Operator or applicant
RWE Npower Renewables
Planning authority
North Lincolnshire
Planning application reference
WF/2011/0734
Turbines
18
Address (REPD)
Land West of Brigg Road, Horkstow,
Council area (by location)
North Lincolnshire
Time to decision
33 weeks
REPD reference
4323

Earlier applications for this site

ApplicationMWSubmittedOutcome
Saxby Wold (Brigg Road) WF/2009/0657451 June 2009refused 7 January 2011

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Elsham Wind Farmwind farm30refused on appeal5.3
Wren Kitchens & Bedrooms, Parrott Streetrooftop solar6.6under construction5.7
Carr Lane Solar Farmsolar farm9approved, not built6.9
Humberfield Recycling Centrebattery storage30approved, not built8.9
Melton Common Wind Clusterwind farm5operational9.2
Melton Waste Parkwind farm5operational9.3
Winterton Road, Roxby Solar Farmsolar farm50application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6434, -0.4661).